Featured Project Return to Projects List
Tallahassee Thomas P. Smith Water Reclamation Facility
Project Information
- Project Location:
- CO
- Status:
- Completed
- Structure Type:
- Sewage / Water Treatment Plant
Scope Of Work
This $172 million CMAR project for the City of Tallahassee included preconstruction and establishing multiple GMPs, as well as the complete construction of facility upgrades. MWH Constructors tailored the project work packages to encourage participation by the local community. These outreach efforts provided employment to over 200 craft workers and created a substantial economic impact of more than $100M per year for the local Tallahassee economy.
The facility’s capacity was nearly doubled from 14.3 to 26.5 mgd, with a future upgrade to 30.5 mgd. The main project goal was to incorporate a more efficient enhanced nutrient removal treatment process to meet new environmental standards. These standards were not only met but exceeded state expectations.