San Jacinto Valley Regional WRF Expansion
Project Information
- Project Location:
- CO
- Status:
- Completed
- Structure Type:
- Misc Project
Scope Of Work
The San Jacinto Valley Regional Water Reclamation Facility (SJV RWRF) Expansion – Title 22 Tertiary Treatment Upgrade and Plant 2 Facilities Project is at the existing RWRF site. The project is the latest upgrade and expansion project at the fully-operational SJV RWRF. The goal of the Project is to upgrade the existing tertiary treatment facilities to meet Title 22 standards and expand the existing Plant capacity from 11-MGD to 15.4-MGD (maximum 30-day average flow). The existing facility remained fully operational during construction of the entire project without a single unplanned outage. The SJV RWRF expansion project is divided into two design packages that are combined into one project; Title 22 Tertiary Treatment Upgrades and Plant 2 Expansion with Plant 1 Modifications.
New Flocculation basins
New Tertiary Chemical Building
Expansion of Chlorine Contact Basins
New Tertiary Effluent Utility Water pump station
Headworks and demolition of the old headworks
Primary Clarifier No. 6 and 7 and splitter boxes
Plant 2 Primary Sludge pump station
Plant 2 primary scum pump station
Ferric Chloride Chemical facility
Bio-filters odor control facility
Aeration basin No. 6