Cherokee Tribal WTP
Project Information
- Project Location:
- Cherokee, SC
- Status:
- Completed
- Structure Type:
- Sewage / Water Treatment Plant
Scope Of Work
Construction of an addition to the water treatment plant to expand the treatment capacity from 3.0 MGD to 6.0 MGD.
Work included:
A pre-treatment building
Office building
Three new pre-treatment units
Two sodium hypochlorite units
One new treatment unit
Upfit of two existing treatment units
Chemical feed systems
Pumps
Piping
Electrical systems
SCADA systems.
The expansion and addition were completed while maintaining the existing systems in operation