USH 41 Reconstruction, Box Culverts
Project Information
- Project Location:
- Brown County, WI
- Status:
- Completed
- Structure Type:
- Bridge
Scope Of Work
The Wisconsin Department of Transportation contracted with Jewell Associates Engineers, Inc. to design the realignment of Beaver Dam Creek to accommodate the expanded USH 41/STH 29 interchange. This $14,000,000 project included designing 10 lengthy multi-cell box culverts, one bridge and two retaining walls, detailed erosion control plans, landscaping plans, planting plans, stormwater management, cross sections, plan and profiles, and grading plans. The engineers at Jewell modeled hydraulic conditions of the creek utilizing HEC-RAS modeling software and also modeled fish passage through several culverts utilizing FishXing software. Jewell has incorporated enhanced habitat features for Northern Pike and will be improving the stream banks of Beaver Dam Creek.
This project included substantial coordination with the Wisconsin Department of Transportation, Wisconsin Department of Natural Resources, Army Corps of Engineers, and the Village of Howard. Jewell has worked extensively at the STH 29/32 interchange and is currently working on Beaver Dam Creek near the point where it enters Duck Creek near Velp Avenue.