Sutter Home Winery
Project Information
- Project Location:
- Lodi, CA
- Approx Contract:
- $20,000,000
- Status:
- Completed
- Structure Type:
- Industrial Maintenance
References
- Client:
- Trinchero Family Estates
Scope Of Work
Sutter Home Winery Bottling and Distribution Facility included the installation of sanitary sewers, process waste sub structures and storm drain lift stations along with electrical vault installation and duct structures. It also included the full grading, de-watering, structural concrete, underground utilities, control building, grounding grid, terminations, special testing, and all substation equipment installation.