Featured Project Return to Projects List
Hertel Avenue Real Time Control Structure
Project Information
- Project Location:
- Buffalo, NY
- Status:
- Completed
- Structure Type:
- Utilities
Scope Of Work
This project was an excavation and removal of two box culverts for the construction of a new real time sanitary sewer control structure at Hertel Avenue & Deer Street intersection for the Buffalo Sewer Authority. The construction manager was Wendel with our own Pinto project manager, Greg Maziarz. We contributed as the general contractor and completed an excavation of 30 Feet with flow rates reaching 1,205 C.F.S.