Sterile Processing Department Renovation

Project Information

Project Location:
Miami, FL
Approx Contract:
$300,000
Status:
Completed - Mar 2012
Structure Type:
Hospital / Nursing Home

References

Owner:
Miami Children’s Hospital
Architect:
HKS Architects, Inc.
General Contractor:
ANF Group, Inc.
Client:
Silvia Perez - Manager, Supply Chain Administration
(305) 669-7228
Miami Children’s Hospital

Scope Of Work

This project is the renovation of an existing Sterile Processing Department at Miami Children’s Hospital which is operational twenty-four hours a day, seven days a week.  The work included the installation of new tile, a revision to the existing walls, new paint, new mechanical equipment, new plumbing fixtures, added fire dampers and the installation of new owner furnished equipment to include a new sterilizer, air compressor, and cart washer.  We performed the work in eleven phases and the operations of the Sterile Processing Department were not interrupted during construction.  ICRA was maintained during construction and temporary partitions were erected at each project phase.  The subcontractors were required to perform all work without introducing any contaminants into the sterile processing department during construction.

Share URL copied!
https://www.thebluebook.com/iProView/5/anf-group-inc/general-contractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.