Arden Middle School Multipurpose Building
Project Information
- Project Location:
- Sacramento, CA
- Status:
- Completed
- Structure Type:
- School / College / University
References
- Architect:
- Rainforth Grau Architects
- Client:
- San Juan Unified School District
Scope Of Work
Arden Middle School’s old multipurpose room was built decades ago and only had the capacity to serve fewer than half of the nearly 1,000 students that now attend the school. The Clark/Sullivan team was able to help grow their school to t the current needs.
Because the 10,145 square foot multipurpose room was originally over budget, C/S reviewed plans with the owner and architect in advance of DSA submittal and provided cost saving options to get the project within budget and moved forward.
Once construction started, there was a one month delay in CMU delivery due to testing requirements. C/S was able to modify the construction sequence and coordinated heavily with our framer and CMU subcontractor to have them work at the same time to keep the project on schedule. By using a lease leaseback delivery method, the district, architect, IOR, and C/S were able to approach this project as a team with the same end goal, to have a successful project.