KM Surveying LLC
Rosenberg, TX 77471
Locations
KM Surveying LLC
Prin.
Key Contacts
Owners, Principals & Senior Executives
Kevin McRae's Bio
Transportation Workers Identification Credentials (TWIC)
Mr. McRae has over 40+ years in the Land Surveying and Land Development field. Kevin has supervised
and managed field and office staff with regard to QA/QC in the daily operations, planning and
execution of control surveys for large land development projects, METRO and TXDOT projects
throughout the Texas Gulf Coast utilizing the latest technology in the surveying industry. Most
projects required the use of GPS as well as other high tech surveying technology. He is highly
experienced in ALTA/ACSM land title surveys for commercial properties, topography, right-of-way
acquisitions and parcel maps, drainage studies, construction and platting in various municipalities
around the Gulf Coast Region.
MASTER PLANNED COMMUNITIES
Mr. McRae has been involved in the following master planned communities and was responsible for
field surveys for control networks required for large acreage developments, including boundary
surveys for defining individual sections, topographic surveys for design, construction layout of
underground utilities, lot grading, layout staking and required as-built drawings for acceptance
throughout Harris, Fort Bend, Brazoria and Galveston Counties.
• Sienna Plantation
• Waters of Avalon
• Lake Olympia
• South Shore Harbor
• Kingwood
• Shadow Creek Ranch
RELEVANT PROJECTS
Intermodal Light Rail Center – North Side of
the City of Houston, Texas – R.P.L.S. for parcel acquisition and topography for design of 12 tracts
consisting of 30+ acres bounded by N. Main Street I-10, and I-45. Responsible for QA/QC of
deliverables per METRO requirements.
St. Joseph Hospital Campus, Houston, Texas –
R.P.L.S. in charge of ALTA/ACSM land title survey of 14 downtown city blocks. Required the
reconstruction of city reference control and boundary corners destroyed by the downtown street
reconstruction project.
Heritage Plaza, Houston, Texas – R.P.L.S. for ALTA/ACSM land title survey of the most recognized
high rise building in downtown Houston.
Houston Center, Houston, Texas – R.P.L.S. for ALTA/ACSM land title survey of five downtown city
blocks. Required the reconstruction of city reference control and boundary corners destroyed by
the downtown street reconstruction project. Required research of the city ordinances at the office
of the City Secretary for allowing encroachment into city right-of- ways.
Tropical Allison Recovery Project for FEMA –
R.P.L.S. responsible for the survey of 900+ structures crossing streams, bayous, and creeks
throughout Houston and Harris County for the development of new FIRM Maps for Harris County.
TXDOT – SH 21, Bryan, Texas – Responsible for parcel surveys for right-of-way acquisition. Monument
new right-of-way and parcel takings and topographic surveys for design.
Free Port LNG Plant
Survey of the intercostal waterway, beach profiles and Freeport Jetty’s for dredging and beach
replenishment along Quintana Beach and Plant expansion.
Port Arthur Placement Area 11
Stakeout and record 93 borehole locations for the dredging of the intercostal waterway adjacent to
the project site. Prepare reports for
Corps of Engineers.
SURVEYING, LLC
PROFESSIONAL LAND SURVEYORS
3902A Reese Road, #C-100 Rosenberg, Tx 77471 TBPLS FIRM# 10178700
713 234-6627 Tel /kmcrae@kmsurveying.com
TxDOT – SH 36 from Caldwell to Milano, Texas
Responsible for aerial mapping control utilizing current GPS technology for parcel acquisition and
design surveys. Project required the recovery of 40+ NGS control monuments throughout a six county
area for a project length of 17+ miles. Responsible for QA/QC of all survey data.
TxDOT – FM 1314 – Porter, Texas – Responsible for control survey required for right-of-way
acquisition and topographic design. This project required boundary survey of more than 75+
separate parcels for the proposed widening of the right-of-way.
TXDOT – Highway 1791, Huntsville, Texas – Responsible for the survey of an 1,800+ acre tract for
the routing of the highway from SH 30 to I-45 including establishing Class II TxDOT monuments for
the new right-of-way. Provided topographic surveys for design and aerial mapping control.
Hobby Business Center, Houston, Texas – R.P.L.S. for ALTA/ACSM land title survey and topographic
survey of a 338+ acre tract near Hobby Airport for commercial development. Required the boundary
delineation of approximately 15 parcels and platting into multiple sections.
Inwood Forest Country Club and Golf Course – R.P.L.S. for the Land Title Survey of a 27 hole, 226+
acre golf course on the north side of Houston.
ALTA/ACSM Land Title Surveys – R.P.L.S. for numerous commercial projects throughout the Gulf Coast
Region, with survey data support provided to other engineering firms for development and
redevelopment of retail and commercial ventures.
Platting – R.P.L.S. for numerous commercial plats with multiple municipalities throughout the Gulf
Coast Region.
Phase 3 of the Automated People Mover (APM) System and Related Infrastructure (elevated Train)–
Terminal B to Terminal A –and Secure Corridor from the North Concourse to the South Concourse of
Terminal A
George Bush Intercontinental Airport, Houston, Texas – As part of the surveying work, the following
surveying services are being provided:
• Establish horizontal and vertical control for surveys and construction tied to the
Houston
Airport System survey coordinate system and datum.
• Preparation of AutoCAD base maps.
• Topographic surveying including overhead structures, utility conduits and lines, and building
features.
• Coordination of the work of subsurface utility explorations.
• The surveyor determined the location and elevations of the underground baggage tunnels.
• High Definition 3D Laser Scanning was employed during the course of this complicated survey.
West Harris County Regional Water Authority-
R.P.L.S. responsible for 2+ miles of a water transmission line requiring defining existing
rights-of-ways, and topographic data for the design of a 16-inch main to connect to 3 Municipal
Districts in west Harris County. Required abstracting of multiple parcels for ownership and
interaction with multiple disciplines.
Houston Independent School District
R.P.L.S. responsible for boundary, topographic utility and Platting of multiple schools being
rebuilt, renovated or replace per the 2007 bond election. Schools surveyed such as Atherton
Elementary, Belfort Academy, Fonville Middle School, Scarborough Elementary, Burbank Middle School,
Kashmere Gardens Elementary School, and Waltrip High School. Various partial surveys of other
schools.
Altair- Survey of contaminated oil field waste used to create road base in the Town of Altair for
the Rail Road Commission. Calculated over 300,000+ cubic yards of material on site. Issued
report and map with 10’ contours.