AEP – Sorenson 765kV East & West Transmission Project

Project Information

Project Location:
Mesa, AZ
Status:
Completed
Structure Type:
Power Generation & Distribution

Scope Of Work

Construct 2 new single circuit 765kV transmission lines. Each line will originate from tap points on the existing Dumont-Marysville 765kV line and will terminate at Sorenson Station. The Sorenson 765kV Extension, West line will be 6.46 miles long and will consist of 33 lattice towers. The Sorenson 765kV East line will be 8.16 miles long and will consist of 37 lattice towers.