L.H. Woods & Sons, Inc.
Vista, CA 92081
Featured Project Return to Projects List
San Diego County Water Authority Pipeline 3, 4 & 5 Relining At The San Luis Rey River
Project Information
- Project Location:
- CA
- Approx Contract:
- $10,000,000
- Status:
- Completed - Jun 2015
- Structure Type:
- Government
Scope Of Work
Relining 259 lf of Pipeline 3, an existing 72” diameter; relining 3,276 lf of Pipeline 4, an existing 90” diameter; and relining 252 lf of Pipeline 5, an existing 96” diameter
The project included fabricating and installing steel liners; environmental fencing; maintaining access roads, SWPPP, clearing & grubbing, bulkheads, dewatering, traffic control, temporary sound walls, welding, grouting between liners, placing field-applied cement mortar lining, Cathodic protection, rehabilitating, and replacing the pipeline’s structures and outlets, hydroseeding, and appurtenant work.