Featured Project Return to Projects List

71st Street Underpass Rehab

Project Information

Project Location:
Chicago, IL
Approx Contract:
$2,000,000
Status:
Completed
Structure Type:
Road / Highway

References

Client:
Norfolk Southern Corporation

Scope Of Work

71st Street was closed west of Cottage Grove Ave. to facilitate the reconstruction of the railroad bridge, which had fallen into disrepair. A temporary shoring system was installed to support the main bridge members allowing work to safely proceed on the bridge.

Removal and replacement of all structural steel support columns and main cross girders at all bents (north curbline, south curbline and middle of the roadway)

Reconstruction of all column foundation bases at the roadway level

Removal and reconstruction of the crashwall protection at the center bent at roadway level

Full enclosure and containment of the existing bridge for lead paint abatement, removal of existing paint coatings and repainting of the entire structure

Removal and replacement of portions of the north and south abutments

Installation of concrete column protection and center bent crashwall concrete construction at street level

Temporary relocation and replacement of underpass lighting utility

Removal and replacement of track level handrail at the east and west sides of the bridge

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/878894/f-h-paschen/general-contractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.