Texas Shot Blast, LLC
San Antonio, TX 78259
Featured Project Return to Projects List
Faubion Elementary School
Project Information
- Project Location:
- Cedar Park, TX
- Status:
- Completed
- Structure Type:
- School / College / University
Scope Of Work
Prep for moisture mitigation system
We were contracted to shot blast to remove existing asphaltic adhesive (tested negative for asbestos). After shot blasting to create a CSP of 3, flooring contractor applied an epoxy moisture mitigation system due to high levels of moisture in the concrete. After installing the epoxy, vct flooring was installed.\
Shot blast 4,992 square feet to Concrete Surface Profile (CSP) of 3
Edge grind perimeter to a CSP of 1-2
Supplied all necessary power to complete project
Project Duration: 1 day including all mobilization (192 miles round trip)