374-380 COMMUNIPAW AVE

Project Information

Project Location:
JERSEY CITY, NJ
Status:
Completed - Oct 2021
Structure Type:
Misc Project

References

Owner:
Not Provided
Architect:
MVMK MINERVINI VANDERMARK MELIA KELLY ARCHITECTURE DESIGN
General Contractor:
SIXBORO CONSTRUCTION LLC

Scope Of Work

12” AND 8" CMU BLOCK FOUNDATION WALL

  1. To install 12”x8”x16” CMU block at foundation (above footing) as per drawing.
  2. To install 8"x8"x16" CMU block at staircases, elevator shaft and first floor partition walls.
  3. To install dur-o-wall wire every 2 (two) courses of CMU as per specs.
  4. To install #5 rebar every 32” o.c.  as per specs.
  5. To fill all block cells with 4,000 psi concrete as per specs.

POWERWALL STUCCO SYSTEM

  1. Complete installation of two layers of felt paper #15.
  2. Complete installation of control joints and plaster stops “j” channels.
  3. Expansion joints will be required to break big walls into small panels for easy to work with.
  4. Complete installation of wire lath mesh.
  5. Complete installation of scratch coat as first layer.
  6. Complete installation of hard coat as second layer.
  7. Complete application of Powerwall stucco will be the third and final coat.
  8. Complete application of backer rod and caulking to all windows where the stucco was applied.

NEW BRICK VENEER INSTALLATION AND REPOINTING

  1. To power wash existing brick.
  2. To do repointing on existing brick at front facade of the building.
  3. Installation of new brick as per specs.
  4. Installation of 1-1/2” rigid insulation.
  5. Installation of wall ties.
  6. Installation of flashing tape.
  7. Installation of weep holes.
  8. Installation of mortar net.
  9. Installation of cast stone as per specs.
  10. Brick washing.
  11. Complete application of backer rod and caulking to all windows where the brick was installed.

TO POUR CONCRETE

  1. To brake existing concrete.
  2. To disposal the waste.
  3. To install wire reinforcing mesh.
  4. To install asphalt expansion control joints.
  5. To forming and pouring new sidewalk and curb concrete as per specs.

Project Images

#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/813380/vp-masonry-drywall-llc/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.