Logo

C.R. Meyer

Share

Muskegon, MI 49444

Company Info

  • Est. 1888
  • Size 500+ Employees
  • Annual Vol Undisclosed

Featured Project Return to Projects List

AGM Phase 2 Expansion Project

Project Information

Project Location:
Middletown, DE
Status:
Completed
Structure Type:
Manufacturing Plant

Scope Of Work

To increase battery production, the supply and installation of 7,000 linear feet of various piping was required for the AGM Expansion Project. The types of piping installed included: PVC, CPVC, Alloy 20, and Carbon Steel Piping.

The project scope of work included demolition of the existing pipe, equipment skids, and chillers; building modifications allowing for larger equipment and tank installations; installation of two 150-ton and two 125-ton York chillers, all handrail, grating, and ladders over and around the new equipment and tanks, and pumps, tanks, instruments, and valves. There was rigging of tanks with limited building clearance in an active Acid room.

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/356457/c-r-meyer/general-contractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.