Rummel Construction, Inc.
Scottsdale, AZ 85255
Featured Project Return to Projects List
Eloy Airport Improvements
Project Information
- Project Location:
- AZ
- Status:
- Completed - Jan 2020
- Structure Type:
- Airport Runway
Scope Of Work
With construction started in Fall 2020, this 8-month long project will be carried out in 16 phases. By the end of this process, Rummel would have completely demolished an existing taxiway and reconstructed a new taxiway alignment approximately 300FT away that meets FAA standards. Drainage issues on the northern side of the airport will be resolved with the installation of a new channel and culvert. Expected at the project’s completion is 55,000CY excavated and exported; 7,500TN of asphalt; 10,500TN of ABC; 950LF of RGRC; and 244LF of double barrel box culverts. Rummel is leading these efforts, along with overseeing the subcontracted full taxiway electrical reconstruction and new chain link security fencing along the property’s eastern side.