Whitnall High School Site Improvements
Project Information
- Project Location:
- Greenfield, WI
- Status:
- Completed - Aug 2012
- Structure Type:
- School / College / University
Scope Of Work
In 2011 work began to completely revise Whitnall High School’s athletic fields. Within our scope of work, C.W. Purpero completed grading for a new football field along with newly constructed bleachers and a concession stand, as well as a new soccer field, softball field, baseball diamond, and athletic track. In addition, excavation was carried out for a 55,000 sq ft wet detention pond. To ensure complete accuracy while grading Whitnall’s football field, we used Millimeter GPS technology on our motor graders.