Broadway Electric, Inc.
Elk Grove Village, IL 60007
Featured Project Return to Projects List
Stephen T. Mather High School
Project Information
- Project Location:
- Chicago, IL
- Approx Contract:
- $6,000,000
- Status:
- Completed - Feb 2013
- Structure Type:
- School / College / University
References
- Client:
- Chicago Public Schools (CPS)
Scope Of Work
The bulk of this project, as subcontractor to Tyler Lane Construction, involved the installation of new electrical service, switchboards MCCs, emergency generator, ATSs, and power and lighting upgrades. Extensive room-by-room equipment upgrades required coordination to ensure the proper delivery of the various items to the proper locations. All work was performed while the building was occupied and in operation.
40 television installations
VGA, Audio, and RCA terminations in 43 locations
42 new projectors
Removal of existing concentrators in 16 locations
4000-series wiremold with 90 degree connections in 27 locations
Old outlet removals from 19 locations
EMT Extensions (30' each of ¾” and 1”) in one location
Wiremold removal from 15 locations
Wiremold installation in 8 locations
VGA, Audio, and RCA extensions from the teacher stations to the projectors, in 42 locations
Removal of old TV (1 hour per location) from 19 locations
Add 30 feet of 4000 Wiremold at back of Classroom (Power, Voice/Data) from three locations
16 other tasks in single locations