Autonation Ford Amherst

Project Location:
Amherst, OH
Completion:
Dec 2019

References

Owner:
Autonation Ford
General Contractor:
Tashcon

Scope Of Work

- Coordinate with T.C. Energy for location of large underground natural gas storage line prior to excavating

- Coordinate with ODOT for approval to work on S.R. 58 and discuss elevation issues

     - Existing culverts are installed properly, however many years of erosion has caused the ditch to infiltrate material. It needs ditched for a distance of approximately 1000 linear feet.               Once I set up the laser and shot everything it needed to be brought to attention prior to pipe installation.

- Delicately remove old CMP culvert while being mindful of nearby utilities

- Safely install new culvert checking for proper elevation along the way

- Backfill, compact, and restore area with approved materials including straw matting and seed