Featured Project Return to Projects List
Cristo Rey High School Lower Level Renovations
Project Information
- Project Location:
- MI
- Approx Contract:
- $700,000
- Status:
- Completed - Sep 2016
- Structure Type:
- Education (K-12)
References
- Architect:
- CM-Partners Architects LLC
- Client:
- Reuben Metzer - Project Manager
Scope Of Work
This former church is a historic building that has been converted to a high school. AGI was contracted to renovate 6,000 SF of the lower level cafeteria of Cristo Rey High School as well as its commercial kitchen. AGI also constructed and installed IT equipment for the school’s mixed media shared community space, also located on the lower level.
Scope Of Work
AGI was able to provide several value added services to the Owner throughout the project.
AGI helped the Owner recognize a significant cost savings by purchasing the kitchen equipment outright, as opposed to having the purchased obtained by the Architect. This resulted in saving the Owner over $20,000.
AGI provided redline drawings to the Owner so that they can now update their as-built drawings.
The IT Media Room did not have a design in place to for the Owner’s plans. To address this critical need, AGI provided suggestions on equipment and audio systems that once implemented, thoroughly addressed the needs of the Owner.