Campbell Green Hybrid Incubator

Project Information

Project Location:
MI
Approx Contract:
$800,000
Status:
Completed - Dec 2018
Structure Type:
Club House / Community Center

References

Architect:
Sedgewic & Ferweda Architects
Client:
Ed Gies - Owner

Scope Of Work

Transforms a house in service of growing community.  From the one story of brick walls in the rear yard rises a translucent solar-facing volume: the Grow Incubator.  The Grow Incubator provides a space for nourishing small businesses, supporting local businesses for perennial flowers and related greenhouse products

Scope Of Work

This project consists of restructuring the existing floor plan to renovate and become an open floor plan with no dividing walls.  AGI installed three I-beams from the basement to the second floor to allow for stability and structural integrity of the house. Footings and support columns were installed to support the I-beams in place.

On the first floor, a 12’ x 15’ storefront glass wall will be installed in the first floor kitchen as the transition envelope access to the greenhouse, which is located at the rear of the house. On the second floor, AGI constructed a mezzanine.  In remaining consistent to the first floor open-feel layout, a 10’ x 10’ storefront wall will be installed to also allow for transition envelope access to the greenhouse.

Masonry and concrete work included pouring new concrete for the entire basement foundation, approximately 1,500 SF, and restoration of the original clay brick wall.  The first and second floors will have concrete flooring with radiant heating throughout. The source of heating will be a combination of a traditional boiler along with solar power derived from the roof panels that will be installed.

All of the windows of the house needed to be replaced.   AGI installed a total of 21 new mahogany framed windows. To address the need for extended life of the roof, AGI installed a patina colored metal standing seam lifetime roof.   The exterior cedar-shake siding and aluminum trim will be installed.

Project Images

#
#
#
#
#
#
#
#
Share URL copied!
https://www.thebluebook.com/iProView/1586410/agi-construction-solution/general-contractors/