HBS Solutions, Inc.
Edgewater, MD 21037
Featured Project Return to Projects List
Rosenbloom Owings Mills JCC
Project Information
- Project Location:
- Owings Mills, MD
- Status:
- Completed - Dec 2017
- Structure Type:
- Club House / Community Center
References
- Owner:
- The Associated
- Client:
- The Associated: Jewish Community Federation of Baltimore
Scope Of Work
As a pre-approved Retro-Commissioning provider through BGE’s Large Building Tune-Up program, HBS Solutions was able to provide a Turn-Key approach that identified, evaluated, quantified, implemented and verified Energy Conservation Measures (ECMs). The ECMs included in this engagement provided improved operational efficiency and resulted in quick returns on investment. Particular attention was focused on low-cost and operational driven savings as core strategies to energy conservation.
The BGE Large Building Tune-Up (LBTU) process involves five phases: the application, preliminary energy study, detailed investigation, implementation and verification phase. Financial incentives are provided through the program that cover up to 75% of the total project costs, with a per project cap of $30,000.
The investigation phase included a Level I & II ASHRAE Energy Audit. This process provided insight through Hands-On investigation
Accomplishments
Energy Conservation Measures Implemented
Optimize HVAC Equipment Operating Schedules
Static Pressure Set Point Reset Strategies
Heating Hot Water Pumps Sequence Adjustments
Improved Reliability of VFD Pumping Control Response
Adjusted Unoccupied Heating Set Points
Eliminated Simultaneous Heating & Cooling
Adjusted VAV Box CFM Set Points
Each ECM implemented was monitored through Measurement & Verification procedures in order to measure their effectiveness and document actual Energy Savings.
Total Cost Share ($) $10,500
Annual kWh Saved 118,828
Annual Electric Savings $22,132
Payback Period .47 years (5.6 Months)