Featured Project Return to Projects List

Glen Hills Middle School

Project Information

Project Location:
WI
Status:
Completed
Structure Type:
Education (K-12)

Scope Of Work

The project starts at 8:00 a.m. on the dot at Glen Hills Middle School. The semi truck carrying the load of cement powder rolls in. About half an hour later, the cement powder starts getting laid over the parking lot that has had the asphalt parking lot that was here pulverized. At this point, all that’s left is the pulverized asphalt and gravel bed mixture.  Now, every square foot gets an application of cement powder at a depth of around 1.5-2” depending on site conditions the day of work.

At 8:55 a.m., the pulverizer starts following behind the cement powder truck.  The pulverizer goes 14” into the existing base material, mixing the powder with the existing base material. Once the two are mixed together, the concrete powder starts reacting, hardening the stabilized base components. It is also at this time that the newly mixed stabilized base is tested for the right moisture. To check for this, a ball of the stabilized base is made and it should fall apart after being bounced in a hand.

After the powder and existing pulverized asphalt/gravel parking lot have been mixed, the base is rolled and compressed by a pad roller driving over it four times for extra compaction. The grader follows the pad roller and smooths everything out so it is ready for the final compaction from the smooth roller, making it ready for the asphalt installation.

By 4:30 p.m., the base stabilization and grading process for this parking lot is complete.

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/1357832/wolf-paving/subcontractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.