Crivitz High School Re-Roof 4

Project Location:
Crivitz, WI
Approx Contract:
$700,000
Completion:
Aug 2019

References

Owner:
Crivitz School District
Architect:
Stantec
General Contractor:
Self Perform
Client:
Thomas White - Director of Buildings, Grounds, & Transportation (715) 854-2721
Crivitz School District

Scope Of Work

Removed the existing Ballasted EPDM Roof and Tapered Insulation System.  Installed a new tapered insulation system, 60 mil Duro-Tuff Membrane, metal edging, and provided a         25 Year NDL Manufacturers Material & Labor Warranty.

Recycled 10 semi-trucks of insulation, and the owner reused the ballast rock for landscaping