Scope Of Work
- This was a Project that had to be done in a specific time due to Semi trucks coming in and out for Freight. The Driveway & Loading Ramp was shutdown for a couple days for everything to be demoed for Construction and poured with Concrete. For the driveway, we poured Concrete up to the existing blacktop that was on site.
- The Concrete mixes we used was a DOT A 4,000 psi & DOT C 5,000 psi mix that would make the driveway able to be driven on in 3 days. With the DOT C mix design, finishing became challenging at times due to the warmer temperatures, sun, and wind. The Driveway & Ramp were poured at 8" thick with Forta Ferro reinforcement. We screeded with our Somero S940 Laser Screed equipped with 3D Profiler System.