01 24 13 - Value Engineering
01 29 83 - Payment Procedures for Testing Laboratory Services
01 31 13 - Project Coordination
01 31 19.13 - Preconstruction Meetings
01 35 16 - Alteration Project Procedures
01 57 13 - Temporary Erosion and Sediment Control
01 57 23 - Temporary Storm Water Pollution Control
01 84 19 - Interior Finishes Performance Requirements
01 85 00.00.01 - Conveying Equipment Performance Requirements
01 87 13 - Equipment Performance Requirements
01 88 16 - Selective Construction Performance Requirements
01 89 13 - Site Preparation Performance Requirements
01 89 16 - Site Improvements Performance Requirements
01 89 19 - Site Plumbing Utilities Performance Requirements
01 89 23 - Site HVAC Utilities Performance Requirements
01 89 26 - Site Electrical Utilities Performance Requirements
01 89 29 - Other Site Construction Performance Requirements
01 91 23 - Interiors Commissioning
01 91 23.13 - Interior Construction Commissioning
01 91 23.43 - Stairways Commissioning
02 05 19 - Geosynthetics for Existing Conditions
02 05 19.13 - Geotextiles for Existing Conditions
02 05 19.16 - Geomembranes for Existing Conditions
02 05 19.19 - Geogrids for Existing Conditions
02 32 19 - Exploratory Excavations
02 58 16 - Snow Avalanche Control
02 58 13 - Snow Fencing
03 08 00.00.01 - Commissioning of Concrete
03 11 13.13 - Concrete Slip Forming
03 35 23 - Exposed Aggregate Concrete Finishing
03 35 26 - Grooved Concrete Surface Finishing
04 08 00.00.01 - Commissioning of Masonry
22 13 23 - Sanitary Waste Interceptors
22 13 26 - Sanitary Waste Separators
22 13 29.33 - Sewerage Pump Basins and Pits
22 13 36 - Packaged, Wastewater Pump Units
22 13 43 - Facility Packaged Sewage Pumping Stations
22 13 43.13 - Facility Dry-Well Packaged Sewage Pumping Stations
22 13 43.16 - Facility Wet-Well Packaged Sewage Pumping Stations
22 14 29.19 - Sump-Pump Basins and Pits
22 14 23 - Storm Drainage Piping Specialties
31 01 10 - Maintenance of Clearing
31 01 20 - Maintenance of Earth Moving
31 01 50 - Maintenance of Excavation Support and Protection
31 05 19 - Geosynthetics for Earthwork
31 05 19.13 - Geotextiles for Earthwork
31 05 19.16 - Geomembranes for Earthwork
31 05 19.19 - Geogrids for Earthwork
31 06 10 - Schedules for Clearing
31 06 20 - Schedules for Earth Moving
31 06 20.13 - Trench Dimension Schedule
31 10 00.00.01 - Site Clearing
31 11 00.00.01 - Clearing and Grubbing
31 12 00.00.01 - Selective Clearing
31 14 13 - Soil Stripping and Stockpiling
31 14 13.13 - Soil Stripping
31 14 13.16 - Soil Stockpiling
31 14 13.23 - Topsoil Stripping and Stockpiling
31 14 16 - Sod Stripping and Stockpiling
31 14 16.13 - Sod Stripping
31 14 16.16 - Sod Stockpiling
31 20 00.00.01 - Earth Moving
31 22 13 - Rough Grading
31 22 16 - Fine Grading
31 22 19 - Finish Grading
31 22 19.13 - Spreading and Grading Topsoil
31 23 13 - Subgrade Preparation
31 23 16 - Excavation
31 23 16.13 - Trenching
31 23 16.16 - Structural Excavation for Minor Structures
31 23 16.26 - Rock Removal
31 23 33 - Trenching and Backfilling
31 24 13 - Roadway Embankments
31 24 16 - Railway Embankments
31 25 13 - Erosion Controls
31 25 23 - Rock Barriers
31 25 53 - Sedimentation Controls
31 25 63 - Rock Basins
31 30 00.00.01 - Earthwork Methods
31 31 19 - Vegetation Control
31 31 19.13 - Chemical Vegetation Control
31 32 19.19 - Geogrid Layer Separation
31 32 19.23 - Geotextile Layer Separation
31 32 13 - Soil Mixing Stabilization
31 32 13.13 - Asphalt Soil Stabilization
31 32 13.16 - Cement Soil Stabilization
31 32 13.19 - Lime Soil Stabilization
31 32 13.23 - Fly-Ash Soil Stabilization
31 32 13.26 - Lime-Fly-Ash Soil Stabilization
31 32 16 - Chemical Treatment Soil Stabilization
31 32 16.13 - Polymer Emulsion Soil Stabilization
31 32 19 - Geosynthetic Soil Stabilization and Layer Separation
31 32 19.13 - Geogrid Soil Stabilization
31 32 19.16 - Geotextile Soil Stabilization
31 32 33 - Shotcrete Soil Slope Stabilization
31 33 23 - Rock Slope Netting
31 33 26 - Rock Slope Wire Mesh
31 33 43 - Vegetated Rock Slope Stabilization
31 34 19 - Geosynthetic Soil Reinforcement
31 34 19.13 - Geogrid Soil Reinforcement
31 34 19.16 - Geotextile Soil Reinforcement
31 34 23 - Fiber Soil Reinforcement
31 34 23.13 - Geosynthetic Fiber Soil Reinforcement
31 35 23.19 - Concrete Unit Masonry Slope Paving
31 35 19 - Geosynthetic Slope Protection
31 35 19.13 - Geogrid Slope Protection
31 35 19.16 - Geotextile Slope Protection
31 35 19.19 - Slope Protection with Mulch Control Netting
31 35 23 - Slope Protection with Slope Paving
31 35 23.13 - Cast-In-Place Concrete Slope Paving
31 35 23.16 - Precast Concrete Slope Paving
31 35 26 - Containment Barriers
31 35 26.13 - Clay Containment Barriers
31 35 26.16 - Geomembrane Containment Barriers
31 35 26.23 - Bentonite Slurry Trench
31 37 13 - Machined Riprap
31 37 16 - Non-Machined Riprap
31 37 16.16 - Concrete Unit Masonry Riprap
31 37 16.19 - Sacked Sand-Cement Riprap
31 72 13 - Rock Reinforcement and Initial Support
31 74 16 - Precast Concrete Tunnel Lining
31 75 16 - Precast Concrete Shaft Lining
32 01 30 - Operation and Maintenance of Site Improvements
32 06 30 - Schedules for Site Improvements
32 11 33 - Cement-Treated Base Courses
32 16 13.13 - Cast-In-Place Concrete Curbs and Gutters
32 16 13.16 - Cast-In-Place Concrete Curbs
32 16 13.19 - Cast-In-Place Concrete Gutters
32 30 00.00.01 - Site Improvements
32 32 34 - Reinforced Soil Retaining Walls
32 71 00.00.01 - Constructed Wetlands
32 72 00.00.01 - Wetlands Restoration
32 91 16 - Planting Soil Stabilization
32 91 16.13 - Blanket Planting Soil Stabilization
32 91 16.16 - Mat Planting Soil Stabilization
32 91 16.19 - Netting Planting Soil Stabilization
32 91 13.13 - Hydro-Punching
32 91 13.16 - Mulching
32 91 13.23 - Structural Soil Mixing
32 92 13 - Hydro-Mulching
32 92 19 - Seeding
32 92 19.13 - Mechanical Seeding
32 92 19.16 - Hydraulic Seeding
32 92 23 - Sodding
32 92 26 - Sprigging
32 92 26.13 - Stolonizing
33 05 16 - Utility Structures
33 05 16.13 - Precast Concrete Utility Structures
33 05 16.53 - Rebuilding Utility Structures
33 06 40.13 - Storm Drainage Schedule
33 12 23 - Water Utility Pumping Stations
33 32 13 - Packaged Utility Lift Stations
33 32 13.13 - Packaged Sewage Lift Stations, Wet Well Type
33 32 16 - Packaged Utility Wastewater Pumping Stations
33 32 16.13 - Packaged Sewage Grinder Pumping Units
33 32 19 - Public Utility Wastewater Pumping Stations
33 40 00.00.01 - Storm Drainage Utilities
33 42 16 - Concrete Culverts
33 42 16.13 - Precast Concrete Culverts
33 42 16.16 - Cast-in-Place Concrete Culverts
33 44 13.13 - Catchbasins
33 44 19 - Utility Storm Water Treatment
33 44 19.13 - In-Line Utility Storm Water Filters
33 44 19.16 - Catch Basin Insert Utility Storm Water Filters
33 44 19.19 - Utility Oil and Gas Separators
33 46 19.16 - Geocomposite Underslab Drainage
33 46 23.19 - Geosynthetic Drainage Layers
33 46 26 - Geotextile Subsurface Drainage Filtration
33 46 33 - Retaining Wall Drainage
33 47 16.13 - Pond Covers
33 47 16.53 - Reservoir Covers
33 47 19.13 - Water Distribution Ponds
33 47 19.16 - Water Retainage Reservoirs
33 47 19.23 - Cooling Water Ponds
33 47 19.33 - Fire-Protection Water Ponds
33 47 23 - Sanitary Sewerage Lagoons
33 47 26 - Storm Drainage Ponds and Reservoirs
33 47 26.13 - Stabilization Ponds
33 47 26.16 - Retention Basins
33 47 26.19 - Leaching Pits
33 49 23 - Storm Drainage Water Retention Structures
33 81 26 - Communications Underground Ducts, Manholes, and Handholes
33 81 29 - Communications Vaults, Pedestals and Enclosures
34 82 19 - Bridge Pier Protection
35 31 29.40 - Stone Groins
35 41 13 - Landside Levee Berms
35 41 13.13 - Stability Landside Levee Berms
35 41 13.16 - Seepage Landside Levee Berms
35 41 16 - Levee Cutoff Trenches
35 42 35 - Slope Protection Bank Protection
35 42 29 - Grout-Bag Bank Protection
35 42 34 - Soil Reinforcement Bank Protection
35 43 29 - Grout-Bag Scour Protection
35 43 34 - Soil Reinforcement Scour Protection
35 43 35 - Slope Protection Scour Protection
35 73 13 - Earth Embankment Dam
41 14 16 - Batch Cars/Transports
41 14 19 - Batch Hoppers
44 41 13 - Packaged Water Treatment Plants
44 41 13.13 - Chemical Packaged Water Treatment Plants
44 41 13.16 - Biological Packaged Water Treatment Plants
44 41 13.19 - Thermal Packaged Water Treatment Plants
44 46 26 - Sludge Thickeners