Iron Mountain is an underground facility in Pennsylvania. Genelco was engaged for a concentrated Commissioning of a new data center and associated nuances of the specific site and support equipment. The new data center housed several work stations, servers and other facilities.

The scope of work included testing and commissioning new data center support infrastructure following installation and successful vendor startup of all major subsystems. Participants included installing contractors and vendor technicians for major equipment such as switchgear, HVAC, BMS, Generator systems, etc. Subsystem performance was tested to specifications and the integrated system was tested to design intent. The entire process was managed by Genelco and validated all items prior to acceptance by CDC and their Client.

Genelco was also responsible for a review of construction documents, shop drawings, organizing and participating in commissioning meetings, preparation of test scripts, functional and integrated testing, equipment, rental and testing technicians, results analysis and report preparation and a final wrap up and training meeting.
?
As part of a Site Assessment, Genelco provided a third party independent review of all infrastructure systems that comprised the electrical and mechanical systems supporting the data center operations. All electrical and mechanical drawings were reviewed to determine the fault tolerance and robustness of the design as well as system concurrent maintainability and redundancy. The two day on-site survey of infrastructure systems included inspecting existing installations and a review of current system operations with site personnel. Following this assessment, Genelco provided a detailed report explaining findings and suggestions where system reliability, maintainability and redundancy can be improved.

Over the course of the project, components and systems commissioned included:
(2) Switchboards with fixed circuit breakers (D48A, D48B) IR and HiPot Testing
UPS input, output, and system bypass boards
(2) 1000kVA UPS modules with Battery Systems and disconnects
UPS Output distribution switchboard
(2) 750kVA Critical Power Transformers
(18) 400A Remote Power Panels (RPP)
(4) 225A Remote Power Panels (RPP)
(1) 400A ASCO Transfer Switch with Bypass Isolation
(1) Chiller Plant (750 ton capacity with 2 Chillers), associated Pumps and controls
EPO System
(4) Chilled Water AHU Units
Leak Detection

Share URL copied!
https://www.thebluebook.com/iProView/9927/cx-testing-services/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.