Mechanical Systems, Inc.
Tucson, AZ 85719
Featured Project Return to Projects List
HVAC System Replacement
Project Information
- Approx Contract:
- $820,000
- Status:
- Completed
- Structure Type:
- Office Building
References
- Owner:
- Architect:
- General Contractor:
Scope Of Work
This project involved replacing the heating and air conditioning system of a 60s-era eight-story office building. Although renovations of this magnitude are rare, the building's inefficient HVAC system justified a state-of-the-art replacement.
To keep the building open during normal business hours, our crews worked nights for nearly nine months. We succeeded on all fronts.
Dividing the project into half-floor sections, we kept the original system operational and added a temporary chiller. Our crews followed a rigorous schedule--we shut down the entire system at the beginning of each shift and finished work every morning by 6 a.m. Even under these constraints, Mechanical Systems completed the project on time and within the budget of $820,000.