Septic System
Project Information
- Project Location:
- Carr, CO
- Approx Contract:
- $40,000
- Status:
- Completed - Jun 2018
- Structure Type:
- Sewage / Water Treatment Plant
References
- Owner:
- Bryan Jones
Scope Of Work
Nicholson Building and Excavating dug and installed the tanks and pump for the dossing septic system. The field was over excavated four feet then pit liner was installed and specialized fill material was added to the field. Geogrid was laid out before the infiltrators were placed in the field. 1.5 inch pipe was placed in the center of the infiltrators and holes were drilled every 4 feet. Dossing systems are used when the native ground percolates too quick and needs to be requlated.