The Berkeley Apartments 4.6
Project Information
- Project Location:
- Arlington, VA
- Status:
- Completed
- Structure Type:
- Apartments & Condominiums
Scope Of Work
Abatement of hazardous materials and complete tear down demolition of twin 5 story 80,000 SF apartment buildings, each building consisting of 137 units.
Asbestos Abatement:
Project Design
Provide permits and notifications for abatement work
Set up containment to state & EPA regulation
Abate ACM as identified
613 friable pipe elbows
1,000 sq ft of duct sealant
73,200 sq ft of non-friable vinyl flooring & mastic
Door caulk from rooftop doors
Demolition:
Mobilize manpower & equipment
Provide daily reports & equipment logs
Provide hydrant tap and permit for dust control
Demolish existing apartment buildings, including slabs, footers, and foundation
Separate and recycle debris to fullest extent possible (by weight 77% of waste stream diverted from landfills)
Transport all debris generated to approved disposal/recycling facilities
Provide certified traffic control for trucks and equipment on and off site
Maintain clean site and street
Rough grade for positive runoff