Village Of Hillburn, 5th Street, Sidewalks & Drainage Project
Project Information
- Project Location:
- Hillburn, NY
- Approx Contract:
- $42,000
- Status:
- Completed - Jun 2014
- Structure Type:
- Road / Highway
- LEED Certification (target):
-
Certified
References
- Owner:
- Village Of Hillburn
- Architect:
- Glenn McCreedy, PE
- General Contractor:
- Scaffidi's Paving And Drainage, Inc.
Scope Of Work
This project consist of installing 85 square yards of 4" thick of concrete sidewalks, 302 Linear Feet of concrete curb, driveway restorations, 100 Square Yards of topsoiling & seeding, removal and restoration of asphalt along existing gutterline, instalation of new drainage pipes, 3 new drainage inlets, 1 headwall and other associated work according to the plans. This project was started on Tuesday June 10th, 2014 and the duration should be two weeks.