Featured Project Return to Projects List
Souther Farm Solar
Project Information
- Project Location:
- Livermore Falls, ME
- Status:
- Completed - Oct 2021
- Structure Type:
- Utilities
Products Used:
Cabling Contrs.--Fiber Optic, Network:
Trenching
Medium Voltage Work
Overhead Line Construction
Underground Line Construction
Commercial Electrical Work
Solar Power
Utility Excavation
Electrical Contractors:
Overhead Line Construction
Underground Line Construction
Commercial Electrical Work
Solar Power
Utility Excavation
Services Rendered:
Electrical Contractors:
Overhead Line Construction
Underground Line Construction
Commercial Electrical Work
Solar Power
Utility Excavation
References
- Owner:
- Revision Energy
- Architect:
- Namaste' Solar
- General Contractor:
- Enterprise Electric
- Client:
- Revision Energy
Scope Of Work
Heavy electrical work associated with a 5,160 kW-DC Solar Project. Our scope was from the combiner panel to the utlity which included (26) inverters, (26) combiners, (2) switchboards, (2) pad muonted transformers, and meduim voltage work back to the utility.