Scope Of Work
During hurricane Irma, a portion of the skylights were torn off the building over the entrance. Instead of replacing the skylights, a metal roof system was installed to repair the damage and also extended along the entire length of the existing skylights.
Five metal beams were welded into place over the hole where the skylights were torn out as a support system for the layers of metal and iso, which also extended onto the skylights that were still in place. Corrugated metal was then installed over the beams and skylights, along with a layer of foam iso board. A water proofing layer installed on top of the iso created a barrier against water leaks for the final layer, which is the white metal roof system. Underneath the beam installation, metal soffit was placed to give it the final look.