O. C. McDonald, Inc.

San Jose, CA 95126

Company Info

  • Est. 1906
  • Size 100-249 Employees
  • Annual Vol Undisclosed

Featured Project Return to Projects List

Apple – Newark Data Facility

Project Information

Project Location:
Newark, CA
Status:
Completed
Structure Type:
Data Centers - Mission Critical

Scope Of Work

36,000 Sq. ft. server facility Phase 1 and Phase 2
• 4600 tons cooling
• 5 Cooling Towers with water storage totaling 320,000 gal.
• 1 Chilled Water storage tank for 100,000 gal.
• Electrical equipment to provide 1.6 MW, N+1 redundancy
• Providing process piping, HVAC, mechanical piping and plumbing.