Louisville International Airport
Project Information
- Project Location:
- Louisville, KY
- Approx Contract:
- $70,000
- Status:
- Completed - Dec 2009
- Structure Type:
- Office Building
Scope Of Work
CAL INC was contracted by Parsons Infrastructure & Technology Inc. (Parsons) to provide labor, equipment, supplies, and supervision to perform the following scope of work at the facility referenced above, located at an Covington (CVG) Air Traffic Control Tower (ATCT). The scope of work included removal of all the existing internal finishes and material including all wall covering, drywall, fiberglass insulation, flooring, suspended ceiling and ceiling grid from inside the link. CAL INC was also responsible for Furnishing and installing an exterior rated Cypher lock on the outside door on the 1st floor of the ATCT.
Highlights of this Project:
Mold remediation work
Work performed at a secure facility