Bove Industries, Inc.
East Setauket, NY 11733
Featured Project Return to Projects List
NYS Route 112
Project Information
- Status:
- Completed
- Structure Type:
- Road / Highway
Scope Of Work
The reconstruction of 3.50 miles of Rte. 112 required an extensive upgrade to the existing underground water distribution and storm-water systems. The majority of underground work consisted of installing approximately 30,000 feet of reinforced concrete pipe, ranging from 15” to 48” in diameter, and to a depth of 30 feet below-grade. In addition to the utility work, the project included 125,000 cubic yards of roadway excavation and the construction of three new recharge basins to handle all the discharge water from the reconstructed roadway. Other road improvement work included placement of 75,000 tons of asphalt pavement, as well as traffic calming and pedestrian safety improvements. Despite all the difficulties in relocating the overhead and underground utilities the project was completed 3 months ahead of schedule.