Featured Project Return to Projects List
James Street Bridge
Project Information
- Project Location:
- Bellingham, WA
- Approx Contract:
- $3,000,000
- Status:
- Completed - Mar 2014
- Structure Type:
- Bridge
Scope Of Work
RAM replaced two century old wooden bridges on James Street with a new single span bridge.
The scope of the project included the bridge replacement, rebuilding and widening the roadways, adding sidewalks, bike lanes, and storm water controls – including a planter on the northbound approach to reduce pollution from storm water runoff. A new parking area was also constructed to allow safe access to the Sunset Pond and recreational trails.
The bridge was open to substantial completion in just 144 days – 7 weeks ahead of schedule.