Turner Industries

Nederland, TX 77627

Company Info

  • Est. 1960
  • Annual Vol $20 million - $50 million

Featured Project Return to Projects List

Air Products and Chemicals

Project Information

Project Location:
Garyville, LA
Approx Contract:
$1,000,000,000
Status:
Completed
Structure Type:
Renewable Energy

Scope Of Work

Technip (Mechanical Phase I) Air Products (Mechanical Phase II) 20 Month Duration 354,000 Workhours 133 Work Packages and an original work schedule of 5 days a week, 10 hours per day. Turner self-performed approximately 85 percent of the work.

• 2,210 Pipe Spools Installed

• 40,279 LF of pipe

• 117 Non-Rotating Equipment

• 51 Rotating Equipment

• 37 Weight Range 70-225K Lbs.

• 416 Reformer Cat Tubes Installed

• 20 Pre-fabricated Modules Installed

• 616 Structural Steel Tonnage

Share URL copied!
https://www.thebluebook.com/iProView/2967/turner-industries/general-contractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.