Air Products and Chemicals
Project Information
- Project Location:
- Garyville, LA
- Approx Contract:
- $1,000,000,000
- Status:
- Completed
- Structure Type:
- Renewable Energy
Scope Of Work
Technip (Mechanical Phase I) Air Products (Mechanical Phase II) 20 Month Duration 354,000 Workhours 133 Work Packages and an original work schedule of 5 days a week, 10 hours per day. Turner self-performed approximately 85 percent of the work.
• 2,210 Pipe Spools Installed
• 40,279 LF of pipe
• 117 Non-Rotating Equipment
• 51 Rotating Equipment
• 37 Weight Range 70-225K Lbs.
• 416 Reformer Cat Tubes Installed
• 20 Pre-fabricated Modules Installed
• 616 Structural Steel Tonnage