Featured Project Return to Projects List
MSY Jet A Fueling System
Project Information
- Project Location:
- KS
- Status:
- Completed
- Structure Type:
- Industrial Maintenance
Scope Of Work
A new terminal on a greenfield provided opportunity to build a safe, efficient hydrant fuel system designed for airport's long-term needs with state---art technology.
New Orleans Fuel LLC retained Argus Consulting to provide planning, design, administration resident for a new Jet A hydrant fuel system. This program was comprised five including a pre-design feasibility study, a ramp hydrant system to serve new North Terminal, a new tank farm fuel transmission system, a hydrant cart test calibration stand, and a further expansion new tank farm.
Phase 1 - Pre-Design Planning
Argus’ to New Orleans Fuel LLC for MSY began with a condition existing fueling system a feasibility study alternates for fuel delivery to proposed new North Terminal.
While functional, existing , dating from early 1970s, had limited storage capacity, was operationally inflexible was beyond its life. Argus undertook a detailed evaluation each system element inbound pipeline, tank farm, transmission pipeline load rack provided detailed assessments suitability for continued use.
In addition to identifying alternatives for delivery fuel to new terminal evaluating each on a technical cost basis, Argus performed two modeling simulation . Using proprietary modeling software based on aircraft type, flight origination destination flight , Argus analyzed airport’s operation to determine instantaneous daily fuel usage. These usages were turn used to “right size” number vehicles proposed systems equipment. Since there is no on airport circulation road connecting the existing tank farm on the southside airport new terminal on northside airport, Argus performed time motion tanker hydrant refueler movements for each alternates to determine lowest overall life cycle cost to deliver fuel to terminal.
Phase 2 - North Terminal
airport’s new North Terminal ramp hydrant system serves 35 gates on Concourses A, B C provisions for future Concourse D. terminal’s Emergency Fuel Shut Off (EFSO) system is zoned into five to minimize impact EFSO events on operation terminal. Given soil condition at terminal , design ramp hydrant system provided consideration for potential future settlement ramp . A remote, aboveground Isolation Valve Station was provided for EFSO functions to address high groundwater table on . This was particularly challenging because design ramp system did not begin until final design terminal was terminal was about to begin. Working under tight time constraints Argus coordinated, design, bid awarded time to allow for ramp system to be constructed advance ramp utilities pavement.
Phase 3 - Tank Farm Transmission System
Tank Farm Transmission System constructed a new larger tank farm next to existing obsolete tank farm connected this new tank farm to ramp hydrant system at new North Terminal. Previously, fuel was delivered by tanker, but this became impracticable because North Terminal’s location.
tank farm design provided a new fuel receipt system, new, larger fuel storage tanks, a transmission pump/filter equipment station. Operational life upgrades were also made to existing load racks. design includes an 800 GPM inbound pipeline receipt filtration train, two 10,000 BBL aboveground storage tanks (ASTs), five 750 GPM transmission pump/filter trains, two over--road tank-truck offload stations tightness testing.
Operational life upgrades to existing four position remote refueler load rack include a new fire foam suppression system refueler load controls.
included design administration a 3,000 GPM transmission system to connect new tank farm on southside airport to North Terminal on northside airport, a 2,600 s.f. Maintenance (OMB). Comprised two 12” transmission lines this system also includes a fiber communication duct-bank to transmit EFSO signals other data between the tank farm terminal. transmission system was constructed by a combination cut cover trenching horizontal drilling beneath Runway 11-29 Taxiways Echo Gulf.
Phase 4 - Hydrant Cart Test Calibration Stand
With existing terminal near existing airside load rack, airport’s need for testing calibrating refuelers was minimal performed by an off-airport contractor. need for on-airport testing calibration hydrant carts increased due to shift from tanker to hydrant system delivery use stationary hydrant carts. To meet this need, Argus designed a hydrant cart test calibration stand co-located with existing load rack to minimize cost. test calibration stand was designed to perform full-flow, overshoot, surge, pressure testing, meter calibration Millipore Aqua-Glo tests. Consisting a 20,000-gallon horizontal aboveground storage tank, 600 GPM vertical turbine pump test/calibration filter separator equipment station, test calibration stand is capable re-certifying 20 hydrant carts per day.
Phase 5 - Tank Farm Expansion
Argus’ current provides for demolition two existing 5,000 BBL aboveground storage tanks two new 10,000 BBL aboveground storage tanks. Pile supported, these new tanks will be enclosed a common concrete containment for space efficiency. Firefighting foam cooling deluge water for new tank farm is provided by provisions recently tank farm design. This also provides a new 2,700 s.f. parts-storage equipment maintenance with additional equipment parking to allow operator to consolidate system operation.