Alexander Orr Jr. Wastewater Plant
Project Information
- Project Location:
- Miami-Dade, FL
- Approx Contract:
- $4,000,000
- Status:
- Completed - Mar 1998
- Structure Type:
- Misc Project
References
- Owner:
- MDWASD
Scope Of Work
The Alexander Orr Wastewater Treatment Plant (Reservoir No. 5) project was completed for the Miami-Dade Water and Sewer Department (MDWASD) and included clearing and grubbing, excavating, dewatering, including sheet piling and trenches, and preparation of site for the construction of a reinforced concrete 20 million gallon potable water reservoir (approximately 705 FT x 265 FT), furnishing and installing four (4) sluice gates (84 in x 84 in); installation of piping and valves, miscellaneous electric work, landscaping and all other related items necessary for complete installation.