D.H. Griffin Wrecking Co., Inc.

Greensboro, North Carolina 27407
View Phone      View Alt Phone


Return to image gallery

Next Image

Misc Project


Bank of America Stadium, Scoreboard Demo

Bank of America Stadium, Scoreboard Demo

DHG contracted by Turner Construction to provide selective structural demolition during this stadium renovation project. Scope of work included the demolition of the two scoreboards leaving the main structural columns and lower levels only; restroom demolition was included to make way for the new AV room. All of the work was performed 200 above stadium seating and concession stands. Very tight timeframe requiring 7 days a week schedule. Work completed safely and on time. Selective demo of the two scoreboards leaving main structural support columns. Included removal of (4) restrooms for new AV room. All work at 200 level overstadium seating and concession stands. Very tight timeframe with significant liquated damages in contract.

View project details for: Bank of America Stadium, Scoreboard Demo

Go to next section: