Featured Project Return to Projects List
Eaa A-1 Flow Equalization Basin
Project Information
- Project Location:
- Palm Beach, FL
- Approx Contract:
- $60,000,000
- Status:
- Completed - Jul 2013
- Structure Type:
- Government
- LEED Certification (target):
-
Platinum
Scope Of Work
NorthStar provided design engineering services for the Everglades Agricultural Area (EAA) A-1 Flow Equalization Basin (FEB) from conceptual through Corrected Final / Ready to Advertise design, and engineering during construction (EDC) services. The 15,000 acre EAA A-1 FEB will temporarily detain up to 60,000 ac ft peak stormwater runoff flows for later controlled release. The concept and implementation of a flow equalization basin is a “first of its kind” project for SFWMD.