Featured Project Return to Projects List
Flatiron Meadows - Erie Parkway – Improvement Plans
Project Information
- Project Location:
- Erie, CO
- Approx Contract:
- $7,000,000
- Status:
- Completed - Jul 2017
- Structure Type:
- Civil & Site Development
References
- General Contractor:
- Fiore & Sons, Inc.
- Client:
- HT Flatiron LP
Scope Of Work
Description of Work: Fiore & Sons, Inc. provided civil contracting services for the Flatiron Meadows - Erie Parkway Improvement Plans. The project included full site package including:
- dewatering
- demolition
- traffic control and management including temporary lane shifts
- erosion control measures
- earthwork and grading (import/export, cut/fill, fine grading, subbase and aggregates)
- regional pond earthwork
- erosion control
- demolition
- storm and all other work
- concrete curb, gutter, sidewalk ramps, asphalt/concrete paving
- Sanitary sewer
- Storm and Waterline construction
- landscaping and irrigation
- relocation of power, gas and telecommunications
- traffic signalization (power, conduit, lights, arms, etc.)
- signage and striping
The project scope also included: Erie Parkway Additions – 12” C900 water mainline, lowering with casing, testing, 45 bends, gate valves and new service taps. Stanley Earth Berm – import/build Earth Berm. Camp Irrigation Piping – 10” SDR, bends and tie-in. Camp/Stanley Driveway – 18” RCP. 42” RCP – 72” Diameter manholes added to alleviate conflicts. 8” SDR35 Under Drain Extension – 8” SDR 35 PVC and bends. Xcel feeder excavation/protection/backfill. Stanley Xcel Conduits/Service – (2) Conduits to transformer & pedestal at Berm, raise existing well, sanitary manholes along with listed punch list items.