Featured Project Return to Projects List
Cleveland Cuyahoga Port Authority
Project Information
- Project Location:
- Cleveland, OH
- Status:
- Completed
- Structure Type:
- Utilities
Scope Of Work
With our multiple low ground pressure machines and long reach excavator, we completed the project and made the site available for dredged material to be offloaded in June.
The notice to proceed was issued in April of 2015 and completion was May 25th. The project included 65,000 CY of wet sand and dirt to be dried and used as structural fill to build the containment berms.
CDF 12, a confined disposal facility, developed to hold the dredged material from the Cuyahoga River, allow for dewatering and then potential reuse of the material.