Featured Project Return to Projects List

Cincinnati Stream Restoration

Project Information

Project Location:
OH
Status:
Completed
Structure Type:
Utilities

Scope Of Work

We reconstructed .5 miles of Indian Creek that had been highly eroded with storm damage and was threatening the stability of US RT 27.

The project consisted of 35,000 CY of excavation and embankment, toe wood bank protection, and 3,000 tons of rip rap placement.

With permitting getting held up and a tight deadline for ODOT to meet EPA requirements, the 4 month expected duration was squeezed down to 6 weeks. We were able to complete the project within 6 weeks and finished under budget.

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/1822741/mark-haynes-construction-inc/subcontractors/
Facebook
X
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.