Featured Project Return to Projects List
Alive Church
Project Information
- Project Location:
- Orlando, FL
- Approx Contract:
- $350,000
- Status:
- Completed - Nov 2021
- Structure Type:
- Church / Synagogue
References
- Owner:
- Alive Church, Inc.
- General Contractor:
- Dennis Gunter, GK Development Group
Scope Of Work
The Project scope is outlined below: installation of seven RTUs and ductwork.
Provide and Install three (3) 25 TON TRANE RTUs THD300G3R0D associated duct work, roof top curbs, crane
Provide and Install one (1) 15 TON TRANE RTUs THD180G3R0D associated duct work, roof top curb, crane
Provide and Install one (1) 7.5 TON TRANE RTUs THC092F3R0A associated duct work, roof top curb, crane
Provide and Install one (1) 10 TON TRANE RTUs THC120F3R0A associated duct work, roof top curb, crane
Provide and Install one (1) 12.5 TON TRANE RTUs THD150G3R0D associated duct work, roof top curb, crane
Supply and Install R6 fiberglass duct
Supply and Install double wall spiral duct
Supply and Install galvanized sheet metal duct with R6 wrap for RTU 5&6
Supply and Install R6 fiberglass duct for RTU-7VAV Boxes
Supply and Install ceiling bath fans
New Thermostats, CO2 Kit, Humidity Sensors, Smoke Detectors
Test and Balance