Bravo Fence
Marietta, GA 30062
Featured Project Return to Projects List
Cedar Crest HOA
Project Information
- Project Location:
- Acworth, GA
- Approx Contract:
- $200,000
- Status:
- Completed - Sep 2018
- Structure Type:
- Club House / Community Center
References
- Owner:
- P3 Painting
- General Contractor:
- Stephen Rediger
Scope Of Work
This job was a total of 7118 ft. and 7228 ft of tear down with 6x6 double dado post buried 3' deep. We used 3/4" x 6" x 6' premium pickets. Type C which is in between the post so the fence has the same appearance on both sides. We were given 6 weeks to finish and we completed the job a week early. This was our first job with P3 and they were very pleased with our work. They continue to use us for all their fencing needs.