Featured Project Return to Projects List
Lake Health Systems | Mentor Wellness Center
Project Information
- Project Location:
- Mentor, OH
- Approx Contract:
- $30,000,000
- Status:
- Completed - Feb 2018
- Structure Type:
- Hospital / Nursing Home
References
- Architect:
- TC Architects
- Client:
- Lake Health Systems
Scope Of Work
AMHigley completed this Health and Wellness Center utilizing Lean Construction and Design / Build Practices. This center includes both a fitness center and medical building. The medical building includes urgent care, diagnostics, Mentor family practice, integrative medicine, occupational services, physical therapy, and sports medicine.
• The project incorporated prefabricated exterior wall panels which saved significant time on the project. (typical installation: 2 to 3-weeks) Actual installation was 4 to 5 days.
• A CONXTECH prefab steel system was utilized, allowing for all structural steel to be set in two weeks and eliminating the need for plumbing.
• The team used pull scheduling which led to increased collaboration between trades and 100% achievement of all monthly milestones targets.
• The project completed with only 10 change orders.
• The project completed 6 weeks earlier due to the design/build and lean construction practices. The schedule savings equated to direct general conditions and staff costs.