Toyota Buffer Yard Expansion

Project Information

Project Location:
Hebron, KY
Approx Contract:
$4,000,000
Status:
Completed
Structure Type:
Storage Facility / Warehouse

References

Owner:
Toyota Motors North America
Architect:
BHDP Architecture, Inc

Scope Of Work

The scope of work included the following:

Excavating/grading, including 30,000 CY of imported dirt fill

Storm sewer – approximately 1,495 linear ft. of piping structures (manholes, catch basins, headwalls)

6” underdrain at edge of pavement

Utilities – underground electric run for light poles

Paving – 800 cu. yd. of concrete for dolly pads (the areas where truck trailers place their landing gear) / 390,000 sq. ft. of heavy duty asphalt pavement (10” of DGA base, 6” of asphalt base course, 1.5” of asphalt surface course)

2,350 linear ft. of K-Rail (jersey barriers) at the rear of all the trucks stalls

Security fence and guardrail

Landscaping buffers planted at the property line (approximately 65 trees)

Construction Duration
5 months

Project Size
601,128 sq. ft. of total disturbed area during excavating and grading
390,000 sq. ft. of paving

Project Images

#
#
Share URL copied!
https://www.thebluebook.com/iProView/1448378/triversity-construction/general-contractors/
Facebook
LinkedIn
Request Brochure

We will send a link to your email address that will download our FREE PDF brochure.